CMPC’s proposed Natureza pulp project in Barra do Ribeiro, Brazil, received a preliminary environmental licence from Rio Grande do Sul’s regulator, Fepam. The licence was formally handed over on October 23.
The R$27 billion development includes a new eucalyptus pulp mill and logistics infrastructure, with R$1.5 billion envisaged for an export terminal at Rio Grande port. CMPC’s existing Guaíba mill would remain in operation.
Fepam described a design capacity of 3 million tonnes of bleached eucalyptus kraft pulp annually. This differs from the 2.5 million tonnes in earlier CMPC project information; the licensing announcement does not explain the difference. The recovery system is intended to supply the mill’s energy needs and export surplus electricity. Projected employment reaches 12,000 at peak construction, followed by approximately 800 direct and 1,500 contractor positions.
The preliminary licence establishes environmental viability at the planning stage and conditions for subsequent approvals. It does not permit construction or operation. CMPC must obtain an installation licence before authorised building work can begin.
The regulator’s review included environmental studies, a public hearing and public submissions. The project also envisages waterway logistics, by-product use in fertiliser production and a green belt around the industrial site.
Licensing conditions and logistics
The preliminary approval covers the industrial development and its AWT waterway terminal. Road transport is planned for wood and chemicals, while the terminal would receive wood and support pulp exports by barge.
The recovery boiler will burn black liquor containing lignin to generate thermal and electrical energy. The project envisages converting sludge and other by-products into fertiliser. Environmental compensation is set at 0.5% of the reference investment value under Brazil’s national conservation-unit framework.
The public hearing took place on January 29, 2026, at Parque Municipal Nenê Naibert in Barra do Ribeiro, with 1,178 people attending and 1,376 YouTube views reported by Fepam. The deadline for public submissions was extended to February 13, giving 60 days in total. Contributions formed part of the technical assessment.
For the installation licence, CMPC must submit detailed engineering and documentation on environmental controls for further review. Fepam stressed technical scrutiny, transparency and public participation. The R$27 billion investment and employment figures remain project estimates; the preliminary approval does not authorise those works to proceed.